ProPM Logo Define Activities    
   
   
   
   
   
ProPM Logo                

The Define Activities process consists of identifying & documenting the specific actions to be performed.

  • To produce project deliverables.

The key benefit of the Define Activities process is to break down work packages into activities;

  • These activities provide a basis for all project work, regarding;
    • Estimating
    • Scheduling
    • Monitoring
    • Controlling

Implicit in this process is proceeding in such a way that project objectives will be met;

  • The process of defining & planning the schedule activities.

The Create WBS Process identifies the deliverables at the lowest level in the WBS - Work Package.

  • Work Packages are typically decomposed into components called activities;
    • Activities represent the work effort required to complete the work package.
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
           
   
   
   
   
   
ProPM Logo    
   
   
   
   
   
ProPM Logo    
   
   
   
   
   
ProPM Logo    
               
Time Management          
Plan execution          
Define Activities          
           
           
Process Inputs          
Schedule Mgmt. Plan          
Scope baseline          
enterprise environmental factors          
organizational process assets          
           
           
Tools and Techniques          
Decomposition          
Rolling wave planning          
expert judgment          
           
           
Process Outputs          
Activity list          
Activity attributes          
Milestones list          
           
           
Process Benefits          
Defining activities transforms the work packages from the Create WBS process into activities;
*  These activities provide a basis for all project work, regarding;
        *  Estimating
        *  Scheduling
        *  Monitoring
        *  Controlling
         
         
         
         
         
         
         
           
   
   
   
   